We’re delighted to be starting this project with Galliford Try and to play our part in delivering a net zero carbon primary school in Stretford, Manchester, which is part of the School Rebuilding Programme.

For Beresford’s, this is our first ever concrete frame project – mostly, we work where the hollowcore is supported via a steel frame, so this is an exciting new challenge for us.

We’ve been brought in to complete the phased prep works – which involves the supply and installation of 4500kgs of loose reinforcement bar to the floor and roof, and timber shuttering. Most of our insitu concrete works projects come through recommendation and this one was no different – so, many thanks to Technic Concrete Pumping for putting our name forward.

Precast Concrete Frames Supplier O’Reilly Precast Ltd
Concrete Technic Concrete Pumping
Steel Bar K B Rebar Ltd

Talk to us about your next project by calling 01335 345111